KEY PROJECT INFORMATION
INVESTMENT
$108462.82
PAYBACK
63 Months
M / SAVINGS
$1,623.33
SYSTEM SIZE
99.88kW
GENERATION
141.09 MWh
YEARLY COST BEFORE SOLAR
YEARLY COST AFTER SOLAR
Kew Golf Club
Project Overview
Kew Golf Club, one of Victoria’s premier golfing destinations, was looking for a cost-effective solar energy solution to reduce its rising electricity costs and lower its carbon footprint. The club partnered with Cyanergy, a leader in commercial solar installations, to develop a customized solar power system tailored to their unique requirements. Glenn, Cyanergy’s expert commercial sales representative, worked closely with the club to ensure the solution aligned with their sustainability goals and financial objectives.
Key Project Details
- System Size: 99.88 kW
- Investment: $108,462.82
- Payback Period: 63 months
- Average Monthly Savings: $1,623.33
- Yearly Bill Before Solar: $52,330.00
- Yearly Bill After Solar: $26,165.00
- Annual Energy Generation: 141.09 MWh
Challenges and Solutions
One of the biggest challenges of this project was the club’s specialized roofing material, consisting of rubber tiles rarely seen in Australia. Glenn and the Cyanergy team took a proactive approach, sourcing a specialized fixing solution from the USA that was compatible with the rubber roof while ensuring full compliance with Australian structural standards. The installation was carefully reviewed and approved by engineers to guarantee safety and longevity.
Additionally, the club had strict requirements for aesthetic appeal. Understanding this need, Glenn and the team opted for Longi All-Black 440W solar panels, which offer a sleek and modern look, paired with a Sungrow 110kW inverter to maximize efficiency and performance.
Outcome
By switching to solar energy, Kew Golf Club has achieved significant financial and environmental benefits. With an annual savings of over $26,165, the club has reduced its electricity bills by 50% while producing clean energy.
This project demonstrates Cyanergy’s expertise in commercial solar power solutions, overcoming installation challenges while delivering a high-performing, visually appealing, and cost-saving solar system.
Thanks to Glenn’s commitment and the Cyanergy team’s innovation, Kew Golf Club is now a sustainable leader in the golf industry.
Contact us today to learn more about how commercial solar can work for your business
Recent Projects
AC Laser | Commercial Solar Installation
A leading manufacturer based in Thomastown, Victoria, turned to Cyanergy to meet their solar energy needs. To reduce their escalating energy costs and increase sustainability, AC Laser invested $90,600 in a 99.45 kW solar system that generates 141.75 MWh annually.
Tixana Pty Ltd
KEY PROJECT INFORMATION CASE STUDY Tixana Pty Ltd Campsie, NSW Download Case Study INVESTMENT $44,920.00 PAYBACK PERIOD 38 Months MONTHLY SAVINGS $907.50 SYSTEM SIZE 40.33 kW GENERATION 51MWh YEARLY COST
New life Aquarium
KEY PROJECT INFORMATION CASE STUDY New life Aquarium Keysborough, VIC Download Case Study INVESTMENT $31,250.00 PAYBACK PERIOD 38 Months MONTHLY SAVINGS $743.33 SYSTEM SIZE 40.5 kW GENERATION 51MWh YEARLY COST
Whites Glenola Hay Far | Commercial Solar Installation
Yearly energy cost before solar $8750.00. Yearly energy cost after solar $428.00
Wyndham Community Schools
KEY PROJECT INFORMATION CASE STUDY Wyndham Community Schools Werribee, VIC Download Case Study INVESTMENT $49,000.00 PAYBACK PERIOD 49 Months SYSTEM SIZE 54.25 kW GENERATION 69.9MWh Wyndham Community Schools The ChallengeMost
Warehouse
Warehouse Energy bills can be a large overhead in business, especially in a warehouse as Toll. The client approaches us about their warehouse lighting upgrade to reduce their overall cost