KEY PROJECT INFORMATION
INVESTMENT
$591,823.71
PAYBACK
37 Months
M / SAVINGS
$15,909.00
SYSTEM SIZE
490kW
GENERATION
752 MWh
YEARLY COST BEFORE SOLAR
YEARLY COST AFTER SOLAR
Uniplas Mouldings International
Over the past three years, Matthew of Cyanergy has collaborated closely with Uniplas on a range of energy-saving products. As part of their partnership, Matt diligently assessed their power costs annually and conducted comprehensive feasibility studies for their facility.
In light of the significant increase in energy expenses over the past two years, they identified a remarkable opportunity for a large-scale solar installation. What makes this opportunity even more enticing is the remarkable reduction in the payback period. Initially estimated at 6-7 years, the payback period has been dramatically shortened to just 3 years, thanks to the favourable trends in energy costs.
To further maximize the benefits, the installation has been strategically divided into multiple stages. This innovative approach has enabled Uniplas to access three distinct sets of subsidies, resulting in a substantial upfront cost reduction of over $190,000.00. Moreover, the efficiency and speed at which the project progressed are truly noteworthy. From the initial consultation to the completion of stage 1, which entailed installing 200kW of solar power, a mere four weeks had elapsed, to the final stage, where a combined total of 490kW was installed to complete the project.
This impressive turnaround time showcases the commitment and expertise of Cyanergy’s team in swiftly implementing sustainable energy solutions.
Matt’s collaboration with Uniplas exemplifies the power of Cyanergy and proactive engagement in driving tangible outcomes. Our shared focus on energy efficiency has not only brought financial advantages to Uniplas but also fostered a greener and more sustainable future.
Upgrade your commercial refrigerated display cabinet
to save between $800 - $900 per year in energy savings as part of the NSW energy saving scheme.
Contact us today to learn more about how commercial solar can work for your business
Recent Projects
Uniplas Mouldings International | Commercial Solar Installation
Yearly energy cost before solar $647,005.00. Yearly energy cost after solar $456,097.00!
Ashfield Bowling Club | Commercial Solar Installation
Ashfield Bowling Club has invested $9,670 in a 32.56 kW solar system, generating 41.395 MWh annually. This initiative saves $805.83 monthly, with a payback period of 12 months, showcasing the club's commitment to sustainability and energy efficiency for its members and the community.
Froliq Early Learning | 26.4kW Solar Installation
Kew Golf Club, one of Victoria’s premier golfing destinations, was looking for a cost-effective solar energy solution to reduce its rising electricity costs and lower its carbon footprint
Multi-Site Age Care Facility Project
KEY PROJECT INFORMATION CASE STUDY Age-Care Facility Project Mitcham, VIC Download Case Study INVESTMENT $60,000.00 PAYBACK PERIOD 52.8 months MONTHLY SAVINGS $1,193.25 SYSTEM SIZE: 60 kW GENERATION 80.652 MWh Age
Warehouse
Warehouse Energy bills can be a large overhead in business, especially in a warehouse as Toll. The client approaches us about their warehouse lighting upgrade to reduce their overall cost
Kew Golf Club | 99kW Commercial Solar Installation
Kew Golf Club, one of Victoria’s premier golfing destinations, was looking for a cost-effective solar energy solution to reduce its rising electricity costs and lower its carbon footprint